Fresh disruption warned as Walsall Sprint works get back under way

The works, part of the Sprint transport project, are expected to cause temporary traffic restrictions, pedestrian diversions and lane closures in Walsall town centre.

Transport bosses have warned of localised disruption as works on a major bus scheme are set to re-emerge in Walsall this week. 

Phase two of the Sprint transport project began Monday, October 5, resulting in ‘improvements’ along Darwall Street and Lichfield Street in the town centre, as well as at the Skip Lane junction with Birmingham Road. 

The project, managed by Transport for West Midlands, was first announced in 2018 and was expected to be completed and open by the 2022 Commonwealth Games. 

The service, when it is eventually complete, will operate along the A34 from Birmingham, through Great Barr and onto Walsall and include routes to Solihull and the airport. 

The tram-like vehicles have been promised to be more reliable, frequent and a greener mode of transport, also helping to ease congestion. 

Phase two will see new bus shelters, highway improvements and resurfacing at the selected locations, and are due to be complete by November 6, 2026. 

The authority has warned of ‘localised disruption’ during the works with temporary traffic restrictions, pedestrian diversions and lane closures.

Phase one of the project in Walsall faced huge criticism from Walsall Council, with members being inundated with complaints from residents due to the road works. 

Council leader at the time Mike Bird described the project as an ‘unmitigated disaster’. 

Some businesses said they were forced to close as a result of the disruption and one even reported losses of tens of thousands of pounds. 

There were also several protests as residents fought to save trees in an area called The Green on Birmingham Road, which eventually led to the route being changed. 

Phase one in Walsall completed in summer 2022, but since then the project has lay dormant.

Transport bosses said in June 2023 that the works so far had resulted in the average bus times between Walsall and Birmingham being reduced by six minutes. 

In both Birmingham and Solihull, phase two of the works started in September 2024. 

Transport bosses attending a scrutiny committee meeting at Walsall Council in February 2025 were still unable to confirm when the project would arrive in Walsall. 

Committee member, Adam Hicken, questioned whether the ‘same people who manage HS2 were managing Sprint as well’. 

Earlier this year the West Midlands Combined Authority approved a £26 million spend on buying the tram-like buses, as well as a further £5.5 million on the ‘buy before you board’ ticketing equipment.

Comment Guidelines

Iconic Media encourages reader discussion on our stories. User feedback, insights and back-and-forth exchanges add a rich layer of context to reporting. Please review our Community Guidelines before commenting.

Local news you can trust
Follow us
© 2026 Iconic Media Group Ltd. All rights reserved.Cookie SettingsTerms and ConditionsPrivacy notice