WATCH: Digging work under way to prepare for rescue of boats caught in West Midlands canal collapse

Work is under way to prepare for the rescue of two boats swallowed by a major breach in the Llangollen Canal in Shropshire.

Construction specialists moved onto the site of the collapse, where two boats remain grounded in a massive hole, earlier this week.

Today (Wednesday, January 14) dedicated equipment is being used to create a ramp to allow the boats to be winched from the 50m hole.

The boats, Sefton and Ganymede, were plunged to the bottom of the giant chasm created by the the catastrophic collapse in the Chemistry area of Whitchurch just three days before Christmas.

Digging taking place in preparation for the removal of the two stranded boats. Photo: Steve Leathplaceholder image
Digging taking place in preparation for the removal of the two stranded boats. Photo: Steve Leath

Incredibly the occupants of both boats emerged physically unscathed from the ordeal - although both have lost their homes while they await recovery and assessment of the state of the boats.

The boats have now been removed.placeholder image
The boats have now been removed.

It is anticipated that the boats will be winched clear of the breach later this week.

Digging taking place in preparation for the removal of the two stranded boats. Photo: Steve Leathplaceholder image
Digging taking place in preparation for the removal of the two stranded boats. Photo: Steve Leath

On Tuesday dedicated work took place to refloat another boat, Pacemaker, which narrowly escaped being sucked into the breach as it opened up on December 22.

Digging taking place in preparation for the removal of the two stranded boats. Photo: Steve Leathplaceholder image
Digging taking place in preparation for the removal of the two stranded boats. Photo: Steve Leath

The boat had been pulled away from the breach earlier this month, and yesterday it was taken further away with workers installing a series of dams around it to create a small marina.

Digging taking place in preparation for the removal of the two stranded boats. Photo: Steve Leathplaceholder image
Digging taking place in preparation for the removal of the two stranded boats. Photo: Steve Leath

Water was then let in from the canal and the boat slowly began to rise. 

After around an hour, the water levels within the marina were level with the canal, the temporary dams were removed and Pacemaker officially rejoined the Llangollen Canal.

The damage caused in the breach is likely to require millions of pounds to fix, and could take the rest of 2026.

Related topics:

Comment Guidelines

Iconic Media encourages reader discussion on our stories. User feedback, insights and back-and-forth exchanges add a rich layer of context to reporting. Please review our Community Guidelines before commenting.

Local news you can trust
Follow us
© 2026 Iconic Media Group Ltd. All rights reserved.Cookie SettingsTerms and ConditionsPrivacy notice