Moog is going places with move to i54 site
The first staff will move into the new landmark Moog site on the i54 site next week as development work passes a major milestone, it was revealed today.
The first staff will move into the new landmark Moog site on the i54 site next week as development work passes a major milestone, it was revealed today.


As the Express & Star was given exclusive access to the 210,000 sq ft aerospace plant on the border of Staffordshire and Wolverhampton – under construction a quarter of a mile from the existing factory in Pendeford – where bosses are preparing for the first phase of relocation.
Organised down to the last detail, the eight-month move will see workers, desks and hundreds of pieces of production machinery transferred to the new factory.
The new workplace is a state-of-the-art site with computer-controlled heating and lighting but with almost one third less space than the factory that has been home to the business since it was called Boulton Paul and moved to Wolverhampton in 1936.
It once produced the wartime Defiant night fighter, but now makes a range of hi-tech aircraft components, such as controls for hydraulic systems, for aircraft ranging from the latest F-35 and Typhoon jet fighters to passengers jets like Boeing's 787 and the double-deck Airbus A280.
David Sharples, finance director at the factory, said: "This development represents a £20 million investment by Moog.
"The site has been designed to make much better use of space, organised around the flow of the work. But, if we need to expand, we also have planning permission for another 50,000 sq ft of space."
US-based Moog bought the factory, then owned by General Electric Aviation Systems, in 2009. The land is still owned by GE, and Moog revealed its hopes to move to its own purpose-built factory on the i54 site.
It became the first company to sign up to the i54, before laboratory firm Eurofins announced its own intentions to move there from its current base in Tettenhall.
Last September it was announced that Jaguar Land Rover would also be taking a large portion of the site to build a £355m engine plant, creating 750 jobs.
Moog started work on its new base last summer, and the aim is to have everything complete by September.
Among a range of facilities, a pump room has been built to provide the 5,000 psi of pressure needed to simulate operating conditions on an aircraft, to test components.
Under the arched roofs of the factory are sealed areas for delicate measuring and calibration work and the bays that will take the testing rigs and computer-controlled manufacturing equipment. Overhead are four cranes, one capable of handling loads of up to five tons, to move machinery and large component assemblies around.
Around 160 of the near-400 strong workforce will work on the shopfloor, while another 80 engineers will be based in offices at the front of the building working in a range of design and technical roles.
Also at the front will be the new large refectory and staff cafeteria, with a patio area outside for the warmer months.
The two-floor office complex at the front also includes meeting rooms that will hold up to 100 people at a time as well as smaller offices. At the moment, the site is a hive of activity, with workers from construction firm McLaren and a string of sub-contractors working, sometimes until after midnight, to ensure that the first Moog workers will be able to move in next week.
In the coming months, around eight lorries a day will be transferring equipment from one site to another. Co-ordinating the move is Mike Rowen, who usually runs the Moog factory in Torrance, California. He said: "Our aim will be to have every piece of equipment back in production within a week. Some may just take a few days, and others might need three weeks, but on average we are aiming for seven days."
Back in the US is his wife and his son, a professional baseball player. He has been in the UK working on the project since October. "I got home at Christmas, and my wife is coming over in a few weeks," he added.
"I'm hoping to see my son in spring training as well." Looking around the factory, he said: "It is a gorgeous building. When you think of all the thousands of decisions that had to be taken, working just from a two dimensional plan, it's incredible to get to where we are now.
"We broke ground in May last year with the aim of starting to move in this February, and we are only a week behind our target date. I think people are going to be really proud to be working here for the next 30 years or whatever."
David Sharples added: "When we were looking at the future we looked at sites like Telford, Lichfield and Stafford but we wanted to keep our very skilled workforce.
"The assistance from the local authorities and from the regional development agency Advantage West Midlands helped make the commercial case for i54.
"At the time it was a risk – we were the first people to say we would move onto the site. Now there is Eurofins and Jaguar Land Rover, and hopefully more to come."